The completion of a single Milestone / Task depends on a series of predecessor tasks or constraints that must be completed first. It is therefore important to be able to analyze the sequence and volume of tasks that constraint work. For a given Milestone / Task, Constraint Network Analysis does this by exposing a network of constraints enabling you to answer the question, “What are all the tasks that would have to be completed to get to that certain Milestone / Task completed?” It will expose what a Milestone / Task is driven by (not what a Milestone / Task drives). Constraint Network Analysis depicts all paths (rather than a single path) leading to the selected Milestone / Task. Basically, if a team desires to start a given task, they will have to work first on all constraint tasks.

Constraints Network Analysis is available in SPS|PM in the Lookahead view and Gantt Charter view. To access Constraints Network Analysis, use one of the following methods:

Method 1: Lookahead View

To access Constraints Network Analysis from the Lookahead view, complete the steps below:

  1. From the Main Navigation Bar select Lookahead, then select Task List.
  1. From the Lookahead view, select the desired Milestone / Task by clicking once anywhere on the Milestone / Task Once selected, the task row will display a blue underline, then from the Floating Menu select Constraints Network Analysis.

    Note: If the selected Milestone / Task does not have any predecessors (is constraint-free), Constraint Network Analysis will automatically be disabled.

  1. Constraints Network Analysis will open in a new window and display the Milestones / Tasks that would have to be completed to get to the selected Milestone / Task completed.
  1. The attributes shown on Constraints Network Analysis can be limited by filtering by: LRM, Forecast, Work Structure, LRM logic, forecast logic, team and team member, dates, and duration. Additionally, data can be visualized by the available Work Structure by selecting: Optimize For.
  1. Constraints Network Analysis default display is the Gantt view but can also be viewed in Network Manager view by clicking the Network View tab.

Method 2: Gantt Charter View

To access Constraints Network Analysis from the Gantt Charter view, complete the steps below:

  1. From the Lookahead dropdown list select Gantt Chart.
  1. From the Lookahead view, select the desired Milestone / Task by clicking once anywhere on the Milestone / Task Once selected, the task row will display a blue underline, then from the Floating Menu select Constraints Network Analysis.

    Note: If the selected Milestone / Task does not have any predecessors (is constraint-free), Constraint Network Analysis will automatically be disabled.

  1. Constraints Network Analysis will open in a new window and display the Milestones / Tasks that would have to be completed to get to the selected Milestone / Task completed.

  1. The attributes shown on Constraints Network Analysis can be limited by filtering by: LRM, Forecast, Work Structure, LRM logic, forecast logic, team and team member, dates, and duration. Additionally, data can be visualized by the available Work Structure by selecting: Optimize For.
  1. Constraints Network Analysis default display is the Gantt view but can also be viewed in Network Manager view by clicking the Network View tab.

  1. To print Constraints Network Analysis, select the desired paper size / orientation under: Optimize for Printing on.
  1. Access to Print menu options may differ based on your browser. For instance, if you are using Internet Explorer, right-click in the white space outside of Constraints Network Analysis and select Print from the menu or simultaneously press the Ctrl and P keys on your keyboard.
  1. The Print Dialogue box opens.
  2. Using the Print Dialogue box, change any desired print settings. Once all relevant printing settings have been modified, click the Print button.

Note: Before printing, it is recommended you confirm the fit to the desired paper size.