A Milestone / Task is created using the same steps and attributes. Unlike a task, however, a Milestone represents the end of a workflow and so does not have any successor tasks. Any Milestone can be turned into a task by specifying another task as its successor. However, this linking is prohibited for a Master Level Milestone as it represents the end of a workflow, so it has no successor tasks and serves as the basis for determining Last Responsible Moment (LRM) dates for a workflow.

To create a new Production Schedule in the Network Manager view, start by inserting a Milestone followed by inserting constraint tasks (see section Insert Constraint Task). If you are revising an existing Production Schedule, you may also need to insert a new Milestone / Task.

To create a Milestone / Task from the Network Manager view, complete the steps below:

  1. From the Main Navigation Bar select the Lookahead, then choose Network Manager.
  1. In the Network Manager view, select the edit filter icon to change any filter settings.
  1. The Network Manager view will display the filter. Select any filter option to add or change.
  1. The Toolbar appears at the top of the Network diagram. The controls allow you to edit, review, and print the Production Schedule. The image below explains each Control.
  1. Create the new Milestone / Task by clicking the New Milestone control.
  1. The Insert New Milestone window opens as shown in the image below.
  1. Populate the Milestone / Task details following the parameters below.
ParameterDescription
Work StructuresSelect values for levels 1-7 of the Work Structures according to the defined Work Structures for your specific project
Team / MemberTeam and member who will own and complete the task
DescriptionStart the description of the task activity with a verb such as ‘Install,’ ‘Develop,’ ‘Formulate,’ ‘Fabricate,’ Approve,’ etc.

Task description should be specific and a measurable quantity, no greater than the Planning Horizon (e.g., one day, one week, etc.)

Level of detail should represent measurable hand-off to the successor activity
Master Level MilestoneIf the milestone is a “Major Milestone” that will be used to measure progress in the Analytics reports, check the Master Level Milestone box
DurationProposed time task will take to complete
Workdays OnlyCheck ‘Workdays Only’ if the task will only be completed during the workweek
MS LRM FinishLRM date when the Milestone / Task must be completed, excluding time buffers
Schedule ReferenceEnter the reference number if used by the project
PriorityDefault set as ‘Normal,’ other options include ‘Low and ‘High’
  1. When finished entering the Milestone / Task attributes, click the Submit button. The Milestone / Task will appear in the Network Manager view. If the new Milestone / Task does not display after clicking the Submit button, click the Refresh control.