A Milestone / Task is created using the same steps and attributes. Unlike a task, however, a Milestone represents the end of a workflow and does not have any successor tasks. Any Milestone can be turned into a task by specifying another task as its successor. However, this linking is prohibited for a Master Level Milestone as it represents the end of a workflow. It has no successor tasks and serves as the basis for determining Last Responsible Moment (LRM) dates for a workflow.

To create a new Production Schedule in the Lookahead (Gantt Chart) view, start by inserting a Milestone followed by inserting constraint tasks (see section Insert a Constraint Task). If you are revising an existing Production Schedule, you may also need to insert a new Milestone / Task.

To create a Milestone / Task from the Lookahead (Gantt Chart) view complete the steps below:

  1. From the Main Navigation Bar select Lookahead, then select Gantt Chart from the Lookahead drop-down list.
  1. Click the Insert New Milestone control.

  1. The Insert a New Milestone window will open.

  1. In the Insert a New Milestone window, enter the Milestone / Task attributes using the guidelines in the table below. If the milestone is a Major Milestone that will be used to measure progress in the Analytics reports, check the corresponding box (Master Level Milestone).
ParameterDescription
Work StructuresSelect values for 1-7 of the Work Structures according to the defined Work Structures for your specific project
Team / MemberTeam and members who will own and complete the task
Task DescriptionStart the description of the task activity with a verb such as ‘Install’, ‘Develop’, ‘Formulate’, ‘Fabricate’, ‘Approve’, etc.

Task descriptions should be specific and a measurable quantity, no greater than the Planning Horizon (e.g., one day, one week, etc.)

Level of detail should represent measurable hand-off to the successor activity
DurationProposed time task will take to complete
Forecast StartDefault is based on a ‘Continuous’ Workflow; other options are used when tasks need to start at a different point than anticipated
Schedule ReferenceDisplays the reference to the milestone the task is constraining
PriorityDefault set as ‘Normal’, other options include ‘Low’ and ‘High’
Workdays OnlyCheck ‘Workdays Only’ if the task will only be completed during the work week
  1. When finished entering the Milestone / Task attributes, click the Submit button. The Milestone / Task will appear in the Lookahead (Gantt Chart) view.